Progress Report - Friday February 16, 2001 ArvinMeritor Automotive Detroit Industrial Plant and Technology Center in the Fort Jefferson Industrial Park
Below is a brief summation covering the important categories relating to the development of the Meritor Industrial and Technology Center. The intent is not to provide an exhaustive review of the week's activities, but a brief synopsis. If a more detailed analysis is required, do not hesitate to call or e-mail.
|
||||||||||||
|
||||||||||||
G2
filed the Baseline Environmental Assessment (BEA) on ArvinMeritor's behalf.
The Michigan Department of Environmental Quality has issued acceptance
letters.
|
||||||||||||
|
||||||||||||
We continue to work with the utility companies on easements over vacated Radamacher. Many of the existing utility poles and lines will remain and be incorporated in the parking or landscape areas of the plant. |
||||||||||||
|
||||||||||||
Campbell/Manix
was selected as the design build contractor.
|
||||||||||||
|
||||||||||||
Complete
|
||||||||||||
|
||||||||||||
Issued January 17 | ||||||||||||
|
||||||||||||
Demolition
complete
|
||||||||||||
|
||||||||||||
The underground work is proceeding. The building structure is up. On schedule. (See pictures) |
TECHNICAL
CENTER
|
|
Design
is for the 80,500 square foot, 4 story technical center is 95% complete.
|
|
Construction budgets are still in the review stage. |