Progress Report - Friday February 16, 2001

ArvinMeritor Automotive Detroit Industrial Plant and Technology Center in the Fort Jefferson Industrial Park

 

Below is a brief summation covering the important categories relating to the development of the Meritor Industrial and Technology Center. The intent is not to provide an exhaustive review of the week's activities, but a brief synopsis. If a more detailed analysis is required, do not hesitate to call or e-mail.

PLANT
Property Acquisition

 

Fisher Guide -

Closed
Library -
Closed
City lot - Closed
Tire repair - Closed
Church lot - Closed


Environmental

G2 filed the Baseline Environmental Assessment (BEA) on ArvinMeritor's behalf. The Michigan Department of Environmental Quality has issued acceptance letters.


Municipal Entitlements

We continue to work with the utility companies on easements over vacated Radamacher. Many of the existing utility poles and lines will remain and be incorporated in the parking or landscape areas of the plant.


Contractor Selection

Campbell/Manix was selected as the design build contractor.


Design

Complete


Building Permits

Issued January 17


Demolition

Demolition complete


Construction

The underground work is proceeding. The building structure is up. On schedule. (See pictures)



TECHNICAL CENTER


Design

Design is for the 80,500 square foot, 4 story technical center is 95% complete.


Construction

Construction budgets are still in the review stage.